Upgrade of the Telephony platform - Move all customer of telephony service on new version by batch
Scheduled Maintenance Report for VTX Telecom
Completed
The scheduled maintenance has been completed.
Posted Dec 03, 2024 - 23:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 03, 2024 - 22:00 CET
Scheduled
* Information

Thanks to our telephony platform which is in "active/active geo cluster mode" we are able to safely upgrade our 4 VoIP platforms instances.

* Migration Actions

We will move the telephony service of all our customers by batch tonight from 22:00 to 23:00.

* Call Impact

None, the change is completely transparent.

* Start of the maintenance

Starting from Tuesday 03.12.2024 at 22:00.
Duration: 1 hour.

* Changelog

Prepare implementation of OAuth2.0 (QR-code), allow to work on new DesktopControl 8 (based on Electron) implementation, allow to implement a fix for transfer handling of devices without REFER Support ( AVM FRITZ!Box), support of new Firmware Nx70, Stability Enhancements.

Reference: TA 36148
Posted Dec 03, 2024 - 09:40 CET
This scheduled maintenance affected: Telephony services.